PSG-1-05:C:1999-01-29:PWi,2:PM send copy of Associated Contractor Agreements to the CEC: PSG-1-07:C:1999-01-30:PSo,2:IST signs the Consortium Agreement and sends a double copy to PM: PSG-1-08:C:1999-01-30:COd,2:IWi signs the Consortium Agreement and sends a double copy to PM: PSG-1-09:C:1999-01-30:ARo,2:Lisnave signs the Consortium Agreement and sends a double copy to PM: PSG-1-10:C:1999-01-30:DMo,2:LMS signs the Consortium Agreement and sends a double copy to PM: PSG-1-19:C:1999-01-31:PWi,2:PM asks CECabout how many % of estimated budget can be transferred between partners without approval: PSG-1-20:C:1999-01-29:ARo,0;URa,2;PSo,0;BJa,0;BGe,0;CGu,0;DMo,2;COd,2;PWi,0;AKa,0:Everyone can send logo proposals to Project Manager (Peter Wieland): PSG-1-21:C:1999-01-29:PWi,2:PM puts the proposals on the Web and sends out a call for vote to PSG members: PSG-1-22:C:1999-02-03:ARo,2;URa,2;PSo,0;BJa,2;BGe,0;CGu,2;DMo,2;COd,2;LBu,2;AKa,2:PSG members send their vote to PM : PSG-1-23:C:1999-02-04:PWi,2:PM evaluates votes and put result to the Web : TC-1-06:C:1999-02-15:ARo,0;URa,0;PSo,0;BJa,0;PJo,0;CGu,0;DMo,0;COd,0;PWi,0;AKa,0:DNV and other partners describe the scenario more in detail:Replaced by Act-TelC-3-01.html TelC-2-01:C:1999-03-03:COd,2:Clemens sends a copy of the ATS toolset to GL,IST, LMS, Marinor and DNV: TelC-2-02:C:1999-03-05:COd,2:Clemens sends a proposal for the agenda and travelas well as hotel information to Peter: TelC-2-03:C:1999-05-10:PWi,2:Peter sends the agenda and the information to allpartners: TelC-2-06:C:1999-03-18:PWi,2:Peter presents a proposal of how to use this server in the future project and where to locate it physically: TelC-3-01:C:1999-03-17:PSo,2;SMa,2;BKa,2;HBr,2;DJa,2;PJ2;ACh,2;CGu,2:All to document their "private" business process models for the Saarbrücken workshop: TelC-3-02:C:1999-03-17:COd,2;HBr,2;DJa,2;EWe,2:WP1 management team to complete the discussions on the WP1 work plan before the Saarbrücken workshop using BSCW.: TelC-3-03:C:1999-03-17:DJa,2:David to announce by e-mail to all partners in task 1.1 that the "private" business process models (see action 1 above) shall be published on the BSCW as soon as they are available.: TelC-3-05:C:1999-03-17:MWi,2:Markus to add to the Saarbrücken agenda the item "Input formats for ARIS".: TelC-3-06:C:1999-03-12:PSo,0;SMa,2;BKa,0;HBr,2;DJa,2;PJo,0;ACh,0;CGu,0;EWe,2;PWi,2:All in WP1 to register for the Saarbrücken workshop ASAP (hotel !!) by sending an e-mail to Clemens.: TelC-3-07:C:1999-03-31:PWi,2:Peter to improve the readability of the acronyms for project members in the action matrix on the web.: WP1-1-01:C:1999-02-15:URa,2:Uwe Rabien as WP1 manager sets up a project plan containing sub-deliverables for WP1 as agreed on during WP1 meeting: WP1-1-02:C:1999-01-27:PWi,2:PM initiates a conference call with some partners to test the technology: MWS-1-07:C:1999-03-24:DJa,2:David sends preliminary of agenda to all members of WP1: PSG-1-11:C:1999-01-30:PSo,0:Marenostrum signs the Consortium Agreement and sends a double copy to PM: MWS-1-01:C:1999-03-22:MWi,2:Markus sends master database to all participants of the workshop.: PSG-1-06:C:1999-01-30:BJa,2:IRI signs the Consortium Agreement and sends a double copy to PM: MWS-1-03:C:1999-04-09:PSo,0;SMa,0;BKa,0;HBr,0;DJa,0;PJo,0;ACh,0;CGu,0:Partners should refine the sub-models at their respective sites: MWS-1-05:C:1999-03-24:DJa,2:David adopts MS-Excel as Format for exchanging the time schedule for the work in WP1: MWS-1-06:C:1999-03-24:ARo,0;ACh,0;AFe,0;AKa,0;BJa,0;CGu,0;COd,0;DJa,0;DMo,0;EWe,0;FPi,0;HBr,0;JHa,0;JBi,0;LBu,0;MWi,0;PSo,0;PJe,0;PJo,0;PWi,0;SMa,0;URa,0;JTh,0:All should confirm participation in WP1-Meeting in Hamburg: PSG-1-12:C:1999-01-30:AKa,2:Neorion signs the Consortium Agreement and sends a double copy to PM: PSG-1-13:C:1999-02-20:PWi,2:DNV countersigns the Consortium Agreement and sends copies back to the partners:Waiting for Act-PSG-1-12 to finish TelC-2-08:C:1999-03-01:BJa,2;ARo,2;PSo,2:Send the consortium agreements to Peter : TC-1-07:C:1999-02-20:PWi,0:PM puts a detailed scenario description on the web:Waiting for Act-TC-1-06 to finish TelC-2-04:C:1999-03-18:ACh,2;COd,2;DJa,2;HBr,2;PSo,2;PJo,2;SMa,2:All partners model their own role in the chosen case: WP1-2-13:C:1999-04-12:PWi,2:Publish the entire work plan from now till June on the BSCW server.: TelC-2-07:C:1999-03-01:URa,2;CGu,2;PSo,2;PJo,2;AKa,2:Send the official letter for the delay of the schedule to Peter: PSG-1-14:C:1999-01-29:PWi,2:PM send Resolution to the CEC as a proposal:Waiting for Act-TELC-2-07 to finish WP1-2-01:C:1999-04-19:HBr,2:Provide outline for T1.1D1 report: WP1-2-02:C:1999-04-19:HBr,2:Publish information about the ISIT platform on the BSCW server: TelC-3-04:C:1999-03-17:COd,0:Clemens to distribute his proposal on accessing the BSCW via the porject web-site to all partners on e-mail.: WP1-2-03:C:1999-04-19:COd,2:Publish information about public key encryption on the BSCW server: PSG-1-01:C:1999-05-23:DMo,2:Dimitris presents MARVIN at International Maritime Forum: PSG-1-18:C:1999-03-31:PWi,2:PM gets addresses and suggest them as review experts to the CEC: TelC-4-3:C:1999-04-30:DJa,2;COd,2:Move BSCW server to IWi: TelC-5-1:C:1999-05-07:JHa,2:Add Product Data description to DNV’s document (Domain processes from Class society’s point of view): TelC-5-4:C:1999-05-07:DJa,2:Changes WP1 plan (additional columns): TelC-5-8:C:1999-05-06:PWi,2:Send Subcontract with Common Progress to all project members: TelC-5-10:C:1999-05-07:PWi,2:Publish information on hotel alternatives for the meeting in Oslo in June.: TelC-5-11:C:1999-05-14:ARo,0;ACa,0;AFe,0;AKa,0;BJa,0;CGu,0;COd,0;DJa,0;DMo,0;EWe,0;FPi,0;HBr,0;JHa,0;JBi,0;LBu,0;MWi,0;NPa,0;PSo,0;PJe,0;PJo,0;PWi,0;SMa,0;URa,0;JTh,0:Send potential objections concerning the reviewers to the PM: TelC-5-12:C:1999-05-20:JHa,2:Performing the review for the MARVIN project in Kavala: MWS-1-02:C:1999-04-09:COd,2:Clemens informs all about UML Link to Rational Rose: TelC-5-9:C:1999-05-14:AKa,0;EWe0;COd,0;SMa,0;ACa,0;DJa,0;PSo,0;PJo,0;ARo,0:Comment the Subcontract with Common Progress: WP1-2-06:C:1999-04-30:DJa,2;ACa,2;SMa,2;HBr,2:Sub-Milestone 1 Delivery of process descriptions (Phase I) to Clemens for VE work:Still open are Act-TelC-5-2 and Act-TelC-5-3 WP1-2-07:C:1999-04-30:ACa,2;SMa,2;HBr,2:Sub-Milestone 2 Delivery of data descriptions (Phase I) to David for T1.2 D1 work.:Still open are Act-TelC-5-2 and Act-TelC-5-3 WP1-2-08:C:1999-04-30:ACa,2;SMa,2;HBr,2;DJa,2:Sub-Milestone 3 Delivery of process descriptions (Phase I) to Emily for T1.4 D1 work:Still open are Act-TelC-5-2 and Act-TelC-5-3 TelC-4-1:C:1999-04-30:DJa,2:Send presentation of scenario to Peter for publishing on project web site: TelC-4-2:C:1999-04-30:ACa,2;SMa,2:Provide description of the repair phase of the scenario description: TelC-5-2:C:1999-05-07:ACa,2:Finish preliminary textual description for Ship Owner, ship crew and tug company role and publish it on the BSCW: TelC-5-5:C:1999-05-07:DJa,2:Publish information on alternative product data modelling formats: TelC-5-6:C:1999-05-14:DJa,0:Inform all WP1 members on the result of the format discussion:Replased by Act-TelC-6-10 TelC-6-1:C:1999-05-24:ACa,2:Finish textual description of process for the tug company role. Put all IST documents in QAP compliant format on the BSCW server: TelC-6-2:C:1999-05-26:ACa,2:Data description of all three roles will be refined by IST, quality ensured by Paulo and published on the BSCW by IST: TelC-6-6:C:1999-05-21:ARo,0;ACh,0;AFe,0;AKa,0;BJa,0;CGu,0;COd,0;DJa,0;DMo,0;EWe,0;FPi,0;HBr,0;JHa,0;JBi,0;LBu,0;MWi,0;NPa,0;PSo,0;PJe,0;PJo,0;PWi,0;SMa,0;URa,0;JTh,0:Remember the 21st of May as the deadline for hotel reservation through DNV: TelC-6-5:C:1999-05-28:AKa,0;EWe0;COd,2;SMa,0;ACa,0;DJa,0;PSo,0;PJo,2;ARo,0:All PSG members asked to come with comments concerning Common Progress subcontract: